The finishing block upgrade, Phase 3 of the multi-phase upgrade was successfully completed at the end of 2017. Russula was responsible for installation supervision, commissioning, on-site operator/maintenance training and provided both on-site and off-site remote support after the start-up to guarantee a smooth transition back to production.
Since Russula is an independent systems integrator, Evraz was offered two drive alternatives from different suppliers. The 6.8 MW ABB Mega Drive-LCI was chosen. It is a robust medium voltage drive used for high power applications ideal for the finishing block.
During an 11-day maintenance outage, the new drive was installed and commissioned. The finishing block successfully returned to operations on December 8, 2017.
Para ofrecer las mejores experiencias, utilizamos tecnologías como cookies para almacenar y/o acceder a información del dispositivo. El consentimiento a estas tecnologías nos permitirá procesar datos como el comportamiento de navegación o identificaciones únicas en este sitio. La falta de consentimiento o la retirada del mismo pueden afectar negativamente a determinadas características y funciones.