The finishing block upgrade, Phase 3 of the multi-phase upgrade was successfully completed at the end of 2017. Russula was responsible for installation supervision, commissioning, on-site operator/maintenance training and provided both on-site and off-site remote support after the start-up to guarantee a smooth transition back to production.
Since Russula is an independent systems integrator, Evraz was offered two drive alternatives from different suppliers. The 6.8 MW ABB Mega Drive-LCI was chosen. It is a robust medium voltage drive used for high power applications ideal for the finishing block.
During an 11-day maintenance outage, the new drive was installed and commissioned. The finishing block successfully returned to operations on December 8, 2017.
To offer the best experiences, we use technologies such as cookies to store and/or access device information. Consent to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Failure to consent, or withdrawal of consent, may adversely affect certain features and functions.