In December 2015, the Gerdau plant in Jacksonville, FL, USA awarded Russula a contract to revamp the bar and wire rod mill drives. The goal of the upgrade is to streamline the mill funcionality and improve the safety of the drives.
Divided by areas within the plant, the electrical upgrade will occur in three phases in order to reduce the downtime and impact on production. Phase 1 included the main mill processing area, in particular the stands and cold shear DC drives and auxiliary equipment AC drives. Phase 2 consists of upgrading the existing drives for the bar mill exit area and Phae 3 the wire rod mill exit area. Downtime will be reduced as Phase 2 and Phase 3 will be implemented alternating uptime. For example, the bar mill exit area drives will be revamped while the mill rolls wire rod and vice versa.
The commissioning of each phase is scheduled to occur during planned shutdowns in 2017.
To offer the best experiences, we use technologies such as cookies to store and/or access device information. Consent to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Failure to consent, or withdrawal of consent, may adversely affect certain features and functions.